In order to solve the pressure brought by the lag of purchased equipment, Jiangdong Shipyard creatively proposed to complete the installation of shafting and rudder water on the mooring state. The plant passed the downdraft ballast test of the ankle chamber to expose the raft shaft to the water surface, and then carried out the underwater installation project according to the axis determined by the ship on the shore and the center line of the rudder line, that is, the “double centerâ€. The plant successfully carried out the installation of the shaft and rudder on five 12,000-ton ships and passed the inspection by GL (German Lloyd's Register) surveyor. The “Double Center†process project was identified by the Science and Technology Department of Anhui Province as the “Domestic First†project in 2007.